A team finishes developing all of their Stories in the first six days of the Iteration, tests them in the following two days, and fixes bugs in the days remaining. How is the team behaving?
Q & A › Category: Agile › A team finishes developing all of their Stories in the first six days of the Iteration, tests them in the following two days, and fixes bugs in the days remaining. How is the team behaving?
A team finishes developing all of their Stories in the first six days of the Iteration, tests them in the following two days, and fixes bugs in the days remaining. How is the team behaving?